New 145-kV transmission line between the Breitenbach substation and the existing Chessiloch (Grellingen) transmission line
Background
To improve the reliability of the power supply, a new interconnection line is to be constructed
between the Aesch and Breitenbach substations. This new interconnection line will ensure that, even in the event of a failure in an upstream grid, power remains available to continue supplying key nodes. Since a pipeline has already been installed from Duggingen to Chessiloch in Grellingen as part of the expansion of the SBB right-of-way, the next step will be to extend it over a distance of 4,800 meters to the Breitenbach substation.

Schedule and Construction Phases
October 2026 – February 2027
Holzgasse – Kaltbrunnentalstrasse – Im Grüt – Baselweg (to the edge of the forest)
January 2027 – February 2027
Tree clearing in the forest section
February 2027 – October 2027
Baselweg (from the edge of the forest) – Gerader Weg – Schmalsteinbettweg – Grellingerweg – Chessiloch (Grellingen) – Dägenauerweg
September 2027 – August 2028
Holzgasse – Rohrrainweg – Rohrgasse – Brislachstrasse
Fall 2028
Completion of civil engineering work
The dates listed reflect the current schedule and are subject to change depending on the progress of construction or unforeseen circumstances.
Unfortunately, traffic disruptions and restrictions cannot be completely avoided during construction. We are doing everything we can to minimize these disruptions and thank you for your understanding.
Building owner and project partners
Building owner | Construction management | Civil Engineering | Specialised civil engineering |
|---|---|---|---|
Primeo Netz AG | Sutter Ingenieur- und Planungsbüro AG | Tozzo AG BL |