New 145-kV cable line between the Lachmatt and Schweizerhalle substations

Background
The existing ‘Lachmatt–Schweizerhalle’ high-voltage line is an oil-filled cable dating from 1986. The cable no longer meets current requirements and has reached the end of its service life.

To ensure the continued security of supply in the region, Primeo Energie is replacing the line between the Lachmatt and Schweizerhalle substations with a new, approximately 3,300-metre-long underground cable. As a first step, two empty conduits will be laid for this purpose.

 

Timeline and construction phases

The necessary civil engineering works will take place along Baslerstrasse, Kästeliweg, Salinenwegli, Düngerstrasse and Rheinfelderstrasse.

Depending on local conditions, the empty conduits will be laid either in open trenches or using trenchless construction methods. The methods used will be horizontal directional drilling (HDD) and pipe jacking.

2026

August 2026
Start of construction at the Lachmatt substation

August 2026 to January 2027
Route: Lachmatt substation – Muttenzerstrasse – Baslerstrasse – Kästeliweg

Autumn 2026 to summer 2027
HDD flush drilling in the Aquabasilea, Salinenwegli and Düngerstrasse areas

2027

Spring to autumn 2027
Further route along Rheinfelderstrasse

Autumn 2027
Completion of civil engineering works

The dates given reflect the current state of planning and may be subject to change depending on the progress of construction or unforeseen circumstances.

Unfortunately, traffic disruptions and restrictions cannot be completely avoided during the construction work. We are doing everything we can to minimise the disruption and thank you for your understanding.

 

Latest news - mid-August 2026 to January 2027
Construction of the cycle path along Muttenzerstrasse, running parallel to the BLT, towards Baslerstrasse/Kästeliweg.

During this construction phase, the cantonal cycle route will be closed and diverted along this section. We ask road users to follow the signposted diversion.

Building owner and project partners

Building owner

Construction management

Civil Engineering

Specialised civil engineering

Primeo Netz AG
Weidenstrasse 27
4142 Münchenstein
Projektleitung: Andreas Isenegger
a.isenegger@primeo-energie.ch
 

Gruner AG
Mühlegasse 10
4104 Oberwil
Thomas Rakun
thomas.rakun@gruner.ch
www.gruner.ch
 
 

Weber AG
Gleis- und Tiefbau
Hofackerstrasse 53
4132 Muttenz
info@gleisbau.ch
www.gleisbau.ch
 
 

follows



 

We are happy to help!